A New Way Forward

On July 30th, we held a congregational meeting to discuss our plans for the rebuilding project of our sanctuary. Since not everyone was able to attend the meeting, we felt it prudent to provide a summary of what was discussed.

 

General Church Information

Information was shared as to the Church's current financial state, which includes

·      A 2023 annual budget of $345,000

o   We are on target with expenses running about $23,000 higher than giving, comparable to previous years.

·      The Church remains debt-free, having paid off our mortgage of over $350,000 in 2020

·      Current assets earmarked for capital and building expenses are about $300,000 in a Vanguard Money Market Account

Updated Building Project Estimates

The building team has spent the past few months reducing the scope of the project to a total cost of $985,000.

·      Estimated Bid from Contractor - $885,000

·      Technology Expenses - $100,000

 

Updated Project Differences

The savings from our initial project proposal of $1.5 million to $985,000 include some significant differences, I’ve outlined some of them below.

·      Structural Changes

o   We will still replace the roof and internal joists.

o   Instead of filling the walls with concrete and using a steel bar for stability, the new plan calls for carbon fiber sheets bonded to the walls to provide stability and strength.

·      Sanctuary Layout Changes

o   We will still remove the steps and stage from the sanctuary and investigate in a movable stage to give us the option to continue worship horizontally or vertically as needed.

·      Narthex

o   We’ll keep the overall size and shape of the narthex the same, instead of moving the wall.

§  We will replace the entry and sanctuary doors with full glass to give more light and an open feeling.

o   We will not remove the asbestos in the Narthex but rather encapsulate it.

·      Heating and Air Conditioning

o   We’ll still need to replace the air conditioning coils, but existing ductwork and air handlers will remain.

o   We’ll also keep our furnaces and baseboard heating.

·      Underground

o   We will still upgrade the bathrooms in the underground as we prepare to utilize that space in the future.

 

Feasibility Study Results and Interpretation

In the Fall of 2022, MUMC engaged with Horizon Stewardship to perform a Feasibility Study, and the results were reported

·      For the 2017-2020 God @ Work Capital Campaign

·      $375,000 was raised

·      2023 Capital Campaign Expectations

·      Reasonable expectation of raising $500,000 - $600,000

Debt Possibilities

Assuming a project cost of $985,000, minus $500k from a capital campaign and $300k in reserves, that leaves about $185,000 to be mortgaged

A 30-year mortgage @ 7.8% interest would be an annual debt service of about $16,000/year over and above regular giving and capital campaign pledges.

 

Next Steps

While no plan is perfect, the building committee believes this is our best option and way to move forward. There are next steps for a project of this magnitude, and some will be taken simultaneously.

·      Reengage our architect to finalize blueprints and restart the bidding process.

·      Reengage Horizon Stewardship for an updated feasibility study and begin a capital campaign

·      Once the building committee receives bids and the feasibility study, we’ll have a congregational church conference to vote to accept the blueprints, contract a builder, take out a building loan and begin construction.

 

No decision will be made without your knowledge and consent, as we continue to navigate moving forward, we'll keep making updates and provide information.

  

Keep the faith!

Jesse Ruch

Pastor, Marlton UMC

Feasibility Study Results and Interpretation - January 2023

Sunday, January 8th, 2023, we held a congregational meeting to discuss our plans for the rebuilding project of our sanctuary. Since not everyone was able to attend the meeting, we felt it prudent to provide a summary of what was discussed.

General Church Information
Information was shared as to the Church's current financial state, which includes

  • A 2023 annual budget of $345,000

  • The Church is debt-free, having paid off our mortgage of over $350,000 in 2020

  • Current assets earmarked for capital and building expenses are about $300,000 in a Vanguard Money Market Account

Building Project Estimates
The project to rebuild our sanctuary has a total expense of approximately $1.5 Million.

  • Bid from Contractor - $1.2 Million

  • Technical Expenses - $100,000

  • Additional Expenses - $300,000

    • In case prices continue to rise

    • Other projects that need to be accomplished at the same time

      • Solar Panels removed and reinstalled from the roof

      • Painting of stairways and hallways

      • Resurfacing the parking lot

      • Landscaping, etc

Feasibility Study Results and Interpretation
In the Fall of 2022, MUMC engaged with Horizon Stewardship to perform a Feasibility Study, and the results were reported

  • For the 2017-2020 God @ Work Capital Campaign

    • $375,000 was raised

  • 2023 Capital Campaign Expectations

    • Reasonable expectation of raising $500,000 - $600,000

Debt Possibilities

  • Assuming a project cost of $1.5 Million, minus $500k from a capital campaign and $300k in reserves, that leaves about $700,000 to be mortgaged

  • A 20-year mortgage @ 6.5% interest would be an annual debt service of about $65,000/year over and above regular giving and capital campaign pledges.

    • With our annual budget of $345,000, that would mean a 5% increase in giving would be necessary to pay the mortgage, if we do not see that increase, we would need to cut back on staff salaries or maintenance and upkeep of the church property.

Moving Forward
I've spoken before on the differences between trusting God and testing God. I believe we're at one of these moments as a congregation. We could take out the mortgage and stretch and hope that we could afford the debt payments, however since we'll also be raising money for the capital campaign, there is a valid concern of fatigue. We may grow tired of constantly talking about money, and if we cannot increase general offerings by another $65,000 a year, we'd need to reduce ministry, which will have a diminishing return.
A more prudent option would be to wait. While no one wants to see us rebuild our sanctuary more than I do, if now is not the time, it is not the time. Therefore, the leadership team will be directing the building committee to investigate reducing or changing the scope of the project in an effort to reduce the cost of the project.
Maybe we can reduce the scope of the project and save money, maybe costs will come down in the next few months, or maybe we need to reevaluate the need to renovate the sanctuary and instead renovate the gym into a permanent sanctuary, replacing the floor with wood, and dismantling the cages and other components of our gym. Someone told me yesterday that they had told their daughter we were meeting to discuss rebuilding our sanctuary and the daughter said, "What are you talking about? We're in the sanctuary already."

No decision will be made without your knowledge and consent, as we continue to navigate moving forward, we'll keep making updates and provide information.

I do ask two things, first, please continue praying for our church, for the leadership of our church, and that God will show us ways to serve the community and look outside of our walls. Secondly, if you have questions, opinions, concerns, complaints, or compliments, please reach out to members of the Building Committee or to myself. We will only move forward with everyone's help and prayers.

Friends, I thank God every day for the opportunity to be your pastor, Alyssa and I pray for you all daily, and I know that we are going to have a great year in ministry.

Keep the faith!
Jesse Ruch

Special Charge Conference

Marlton UMC will be having a special Charge Conference 10/27/2021 at 7:30 pm. The Zoom information can be found below. There are a few necessary documents:

The first is the report from the Sanctuary Rebuild Team explaining the work and process they've been performing. Click here.

The second is the Resolution we are voting on during our meeting tonight. Click here.

If you would like a copy of the Architect’s proposal, please reach out to the Church Office or Pastor Jesse.


As a reminder, the Charge Conference is open for attendance to all members of the Church, but only members of the Church Council may vote.

MUMC Charge Conference

https://us02web.zoom.us/j/87039631528

September 14 Report

Monthly Committee Report

Committee:  Rebuild Task Force

Submitted by: Lisa Taylor & Tim Gunner

Date: 9/14/2021

Recent Activities and Accomplishments

  1. Held meetings on 6/10/21 (team), 6/24/2021 (team), 7/15/21 (team), 7/18/21 (with DS Hector Burgos), 8/25/21 (with interested architect), and 8/31/21 (with interested architect).

Short-term Goals (one - three month outlook)

  1. Select and engage architect to assist in planning.

  2. Establish total Target Budget for project, including new “Rule-of-Thumb” Capital Campaign funds.

  3. Plan for and hold listening sessions with the church community to elicit input on their vision for the new space.

  4. Continue to meet at least twice monthly.

Long-term Goals (three month - 1 year)

  1. Advance planning into Concept and Design Development phases.

  2. Expand project plan and timeline, to include:

    1. Permitting Requirements

    2. Financing/Capital Campaign Planning

    3. Advancement of design to Construction Documents

    4. Proposed Construction Schedule

Concerns / Issues for Council

  1. None at this time.