September 14 Report

Monthly Committee Report

Committee:  Rebuild Task Force

Submitted by: Lisa Taylor & Tim Gunner

Date: 9/14/2021

Recent Activities and Accomplishments

  1. Held meetings on 6/10/21 (team), 6/24/2021 (team), 7/15/21 (team), 7/18/21 (with DS Hector Burgos), 8/25/21 (with interested architect), and 8/31/21 (with interested architect).

Short-term Goals (one - three month outlook)

  1. Select and engage architect to assist in planning.

  2. Establish total Target Budget for project, including new “Rule-of-Thumb” Capital Campaign funds.

  3. Plan for and hold listening sessions with the church community to elicit input on their vision for the new space.

  4. Continue to meet at least twice monthly.

Long-term Goals (three month - 1 year)

  1. Advance planning into Concept and Design Development phases.

  2. Expand project plan and timeline, to include:

    1. Permitting Requirements

    2. Financing/Capital Campaign Planning

    3. Advancement of design to Construction Documents

    4. Proposed Construction Schedule

Concerns / Issues for Council

  1. None at this time.